How an AusNet connection is priced: basic, standard and negotiated connections, the cost calculator, the EnergyConnect portal, offer times and what to ask.
An AusNet connection costs little where a low voltage pole is already close and the right side of the street, and a great deal where AusNet has to extend its network to you. AusNet sorts every job into a basic, standard or negotiated connection: basic and standard connections come at set, regulator approved prices, while a negotiated connection, which is what most rural blocks with no line nearby need, is priced for your site. AusNet's online connection cost calculator gives a quick estimate, and the application itself goes through its EnergyConnect portal. If the negotiated price is large, price an off grid system beside it before you decide.
Who does AusNet cover?
AusNet Services is the electricity distributor for eastern Victoria. Its connection policy, which applies from 1 July 2026, says its network serves about 810,000 connection points across more than 80,000 square kilometres of eastern Victoria. If you are west of that, around Trentham and much of central and western Victoria, your distributor is more likely Powercor, and our article on Powercor connection fees and the application process covers that network. Your bill, or the tag on a nearby pole, tells you which one you have.
How is an AusNet connection cost worked out?
It depends on which of three classes your job falls into. AusNet's connection policy sets them out:
- Basic connection. A routine connection up to 100 amps: an overhead service cable to an existing low voltage pole within the length the Victorian Service and Installation Rules allow, on the same side of the street, without crossing another property, or a connection into an existing pit or pillar on your boundary. These are charged at a fee the Australian Energy Regulator approves.
- Standard connection. An underground extension of up to 40 metres from an existing low voltage pole to a new pit at your property, for one or two customers. It carries a pre calculated capital contribution set out in AusNet's model standing offer, with extra charges for things such as crossing more than one road. It does not apply on single wire earth return (SWER) lines, and the low voltage supply must be within the set distance.
- Negotiated connection. Everything else, including any job that extends or upgrades the network. AusNet works out a capital contribution from its incremental costs for your connection, less the network revenue it expects to earn from you.
We could not find a published table of rural extension prices on AusNet's site when we looked in November 2026, so for a negotiated job the calculator and then a firm offer are the way to a number.
How does the AusNet connection cost calculator work?
The calculator is on AusNet's website. You accept the terms, choose a new supply or a change to an existing one, pick single phase or multiphase, say whether the land is subdivided, and enter the address. AusNet says it gives a quick estimate for supplying power or moving a pole, and that it applies to residential connections and small power requirements only.
Its terms are clear that the estimate is not final and not a binding offer. After the estimate you still submit an electricity supply request in EnergyConnect, and AusNet assesses it and makes a firm offer. The calculator stores nothing, so screenshot your result.
What are AusNet's connection fees beyond the works?
Three things can be added to the cost of the network works:
- Assessment or estimate fees. For jobs that need network changes, or a property with restrictions such as cultural heritage or bushfire risk, AusNet asks for a preliminary estimate first. It says the assessment fee is deducted from your construction cost if you go ahead.
- Upstream augmentation. The connection policy says you only pay toward upgrading the shared network if your maximum demand is above 10 kVA on a SWER line, or above 100 amps per phase on a multiphase low voltage supply. Rural SWER customers who want more than 10 kVA should expect that charge.
- The pioneer scheme. If your connection uses an extension another customer paid for, you may owe them a reimbursement based on the asset's depreciated value over 20 years. AusNet's policy sets the minimum reimbursement at $1,444 for 2026.
AusNet's online offer terms say the price shown excludes GST, so check which way any figure you are given is stated.
What is the AusNet connection process?
AusNet's residential connection process has six steps:
- Create an EnergyConnect account. Homeowners use a residential account; electricians use an industry account. AusNet recommends residential customers have an electrical contractor handle it for them.
- Submit the application through Application Quickstart, with the property address, sketches, any subdivision plan and details of big electrical loads. Ask for a preliminary estimate or a firm offer.
- Pay the initial fees, by card at the end of the application or by invoice to the financially responsible person you nominate. AusNet starts work only once payment is in, so a late payment delays the job.
- Design and offer. For most residential jobs a project manager organises design and costing, then sends an offer letter, contract and invoice.
- Accept and build. Once you sign, the job goes to construction and you get an estimated completion date.
- Supply available, then the meter. Your registered electrical contractor submits a new meter installation request with a signed Certificate of Electrical Safety, your retailer raises a service order, AusNet creates the National Meter Identifier, and its crew installs the meter.
How long does an AusNet connection take?
For basic and standard connections, AusNet's policy says it will use best endeavours to make an offer within 10 business days for a basic connection and 20 business days for a standard one, after a site assessment that can itself take up to 10 business days. For negotiated connections its residential page gives no set time and says it depends on the complexity of the project. On a rural extension, allow months, not weeks, and start well before the build.
Can someone other than AusNet do the work?
Partly. AusNet's policy says that tasks such as auditing third party designs and connection assets stay with AusNet, but most other work, including tendering and building an extension, is contestable. You can use an Approved Contractor instead of AusNet for project management, some design and construction, and ask AusNet to run the tender for you for a fee. AusNet approves all designs and takes ownership of the finished assets. The policy lists line distance, environmental issues such as trees, equipment size and council requirements as the things that drive the cost of that work.
Everything on your side of the point of supply, the consumer mains to your switchboard and the switchboard itself, is yours to pay for and must be done by a licensed electrician. Never dig near or work under powerlines yourself.
When is off grid worth pricing against an AusNet quote?
Whenever the negotiated offer is large, or your block sits on a long SWER line where capacity is tight. An off grid system has real costs of its own, but no capital contribution and no supply charge. Our off grid vs grid connection page shows how to set a connection quote against a stand alone design, and our Powercor connection cost page has published extension prices that give a feel for the scale of rural line work.
Mick McDonald
Technical Director, Trentham Energy